Back-to-school campus repaving schedule
Repaving happening now on campus
August 14, 2014
Just in time for the start of the school year, repaving crews are all over main campus. Below is a list of repaving projects, courtesy of COD’s facilities department.
• Aug. 1 through Aug. 14 – Concrete repairs along Tallgrass and at intersection near SSC, between Fawell Lot B and C. Refer to Green area on attached map.
• Aug. 4 through Aug. 6 – Asphalt sealcoating along eastern half of College Road. Refer to Yellow area on attached map.
• Aug. 6 through Aug. 7 – Asphalt sealcoating along western half of College Road and southern section of Prairie Drive, near the staff lot. Refer to Light Blue area on attached map.
• Aug. 9 through Aug. 10 – Asphalt sealcoating along southern section of Prairie Drive, from intersection of Tallgrass and Prairie going south to just before the staff lot. Refer to Dark Blue area on attached map.
• Aug. 11 through Aug. 14 – Asphalt sealcoating of College Lot 1A, eastern section of College Lot 1 and College Lot 5. Refer to Orange (Salmon) areas on attached map.
• Aug. 16 through Aug. 17 – Asphalt sealcoating of Fawell entrances between Fawell Lot A, B, C and D and the entrance off of Lambert Road at Tallgrass Road. Refer to Pink areas on attached map.
• Dates TBD – Red areas on the map are other areas requiring attention; updates will come at a later date.
Public transportation is also affected by the repaving projects.
• PACE Bus, Aug. 1 through Aug. 17 – The PACE Bus stops along Tallgrass Road will not be available. Bus stops will be relocated to two locations off of Fawell, between Lot A and B and between Lot C and D. Refer to map for locations.